Sunday, April 15, 2018

Construction: Weeks 18-22 (Including move-in!!!!)

Well, this is a much-delayed post.

My cabin got finished (YAAAAY!) and I moved in (YAAAAAAY!) in mid-February (YAAAAAAAY!)

I moved in the midst of an extremely large and demanding work project, which meant that my first several weeks in my home felt like camping. There was no time to get things organized and properly placed (tasks that are not my forte at the best of times and therefore would have consumed a lot of resources that I did not have available) and there was certainly no time for blog posts. But I have hot and cold running water, electricity and Internet, a bar fridge, an induction hot plate, a mattress and my awesome desk and kneeling chair and so I was good to go.

The last weeks of construction and first few weeks of living in my home felt surprisingly fragile to me. The pieces left to do in the last stages were very small, but they felt more overwhelming than many of the bigger elements that had been tackled toward the beginning of the process. I don't know if it was because I was tired, or had less time free from desk work, or felt daunted by the enormity of the transition facing me, or because of my erratic hormones and mood swings (most likely a combination of all of those things), but I felt delicate and teary.

Fortunately, I was able to feel the feelings and do the work and make it into the cabin. I love it and feel very contented and peaceful there. Which is not to say that I don't get tired and cranky and stressed or anything like that, but I feel like I have the space I need to be myself and feel safe in that, and that is an awesome feeling.

Having the floors stained and polished was a gift from my Mom. The floors are one of my favourite things about my house – handsome and easy to clean.

The amazing contractor who stained and polished my floors added a lovely rectangle at each door at my request. I don't know why, but for some reason, these boxes remind me of the department stores I went to as a child: Eaton's and Simpson's. I don't know why that should feel like a good and comforting thing, but it does.

And these beautiful stripes in my bathroom/mechanical room. 

One of my tasks was to sand and stain the material for the wood trim. I should have done it as soon as the trim material arrived, but I didn't and ended up having to rush it at the last minute before the carpentry crew came back in to install it.  

Painting the bathroom door

Forsythia: a gift of spring from a dear friend.

Getting so close! The trim and kitchen cabinetry got installed and only the electrical and plumbing finishing remained.


The bathroom door got hung with awesome hardware made by the blacksmiths at Ross Farm Museum. 
The back of the bathroom door – distressed.
The toilet and shower got installed. The tiling and the bathroom sink are going to have to wait until more money, time and energy are available. The water runs. Some of it is hot. This is more than good enough. (And yes, I do have a shower curtain now, I just don't have a photo of it on hand.) 



Everything including the kitchen sink! Complete with running water.

And the shelving unit on the reverse of the kitchen counter/shelves which serves my office space. Complete with an electrical outlet that was pretty awkward to install. My electricians had to do some super problem solving. They were very gracious about it. 
Move-in day! While I did spend a few nights at my house during the transition, it wasn't really home until Salinger moved in on February 15th. Here he is, settling in for his first night. It didn't take him long at all to adjust; he also seems to love our little home.
I had plenty more help during this transition. Help painting, help moving, listening ears and leaning shoulders.

On the day of my occupancy permit inspection, one of my tender-hearted friends helped me move some furniture from my tiny house and shed into the new cabin. We talked and cried and jumped up and down together. I could have hugged the building inspector when she okayed everything – no, wait, I DID hug her (with her permission). There were no snags and I felt again my deep gratitude to all of the dedicated and professional contractors who built my home as if it were there own, with care, precision and kindness. And I was grateful for the more-or-less successful job I had done impersonating a general contractor – I had acquired and supplied all of the necessary paperwork, we had ticked all of the necessary boxes and done everything we were supposed to do.

The cabin is lovely to live in. It is warm. It is bright. It is airy. It is beautiful. It is simple. Everything works.

There are many finishing touches that need to be added. Now that my very hectic work schedule has slowed up, I need to move in properly. I need to move some pantry shelving and book shelves from my tiny home into the cabin. I need to figure out where things are going to go. I need to find the bag of hardware that will let me put my bed frame together. I need to apply linseed oil and varathane to my kitchen/office cabinets and a few coats of varathane on the window sills, too. I need to set up my turntable and move my records in. I need to make myself fully at home.

Salinger: showing his appreciation for the beautiful, wide windowsills (and not so much for the view of winter outside... )
Eventually, as time and money are available, I will have the shower tiled, the bathroom sink installed, and a deck built. This summer, I will try to do as much as I can to contribute to the healing process for all of the cuts and scars on the land that were caused by the construction.

In good time, I expect that the Crooked Wood, Salinger and I will all find our stride to integrate and grow together.

Monday, October 23, 2017

Construction: Weeks 4 and 5

BIG Weeks!

Weeks 4 and 5 were two major weeks. I was too overwhelmed and busy during and between them to write a blog post, so am putting both weeks together in one post now (at the beginning of Week 6). 

Somewhere in the middle of it all, Salinger and I reluctantly moved house, back into our winter digs in Lunenburg. While we are incredibly lucky to have these friendly and comfortable accommodations available to us for the third winter in a row, it was still a bad wrench to leave The Crooked Woods. But my little tiny house was getting chilly and starting to have problems with moisture and condensation and it was time to head for central heating.

Week 4

Week 4 was SLAB WEEK! This was one of the most nerve-wracking stages of the build so far. Pouring concrete is something you want to get right the first time. Second chances at a pour are virtually impossible. Also, if the cement truck can't access the site, there's a big financial penalty and then more work to do to make the site accessible. 

Fortunately, the cement truck was able to get back to the form on its first attempt, thanks to my amazing friend who widened out the driveway and cut a low limb off the big maple during Week 1.
Distributing the cement to the rear section of the form is heavy work, done by wheelbarrow. The work speeds up once the concrete can be poured directly from the truck's chute into the form.
All poured, partly trowelled
Power-trowelling!
The finished slab. I love the marbled look it has. 
The slab needed to be kept wet for three days to discourage cracks from forming. My rain barrel, a bunch of bed sheets and a big tarp helped with this task. Salinger putting his fluffy backside on the wet sheets was probably counter-productive, but very, very cute.
The ever-deepening chill was a big factor in deciding that it was time to move out to my friend's house in Lunenburg. Here is the radiant heater running full blast in the tiny house while I tried to get some desk work done in the early morning on one of my last days living on site...
The sub-contractors who worked on the slab were fantastic to have on site, continuing my lucky streak of skilled and friendly people working on this project.

Week 5

With the slab poured and set and inspected, the framing could begin. There was a risk of rain on Monday, so the work began on Tuesday, and holy cats, did it ever go quickly with four people on the crew and four days of gorgeous fall weather!!! 

Day 1 of framing
Detail, Day 2
End of day 2!
I was stuck in Lunenburg doing desk work on Day 1, but managed to get to the site to spend the morning on Day 2 and then stopped in for quick visits on Day 3 and again on Day 4. 

I was delighted on Day 2 to watch how the four-person crew functions as a well-oiled machine. Everyone had their tasks to meet the inter-locking requirements of the build. Boards needed to be selected and cut and placed and secured and I found it a graceful, intricate dance to watch. And I love the energy with which the crew works – music on the radio, banter back and forth, questions and answers – it all seems to flow with ease and enthusiasm. 

The best contribution I could make was to stay out of the way! So, I turned my hand to sorting out a bunch of paperwork to do with the build and making sure that all of the permits and plans would be readily accessible when I wasn't there. 

I had an unsettling feeling on Day 2. I walked around inside the framed space and was filled with a sense of panic – "It is TOO small!" I thought. "What have I done? What am I doing? I'm having something built that I'm going to HATE living in. Oh NO!!!!!"

Day 2, side view

But then, weirdly, when I came back at the end of Day 3 and two of the walls were sheathed with OSB, enclosing the building somewhat, it felt larger, rather than smaller. I felt perfectly comfortable, and thought "Oh, yes, this is exactly what I thought it would be like; this is plenty of room!"

And when I came back on Day 4, when all four walls were closed in to a height of 8 feet, the space felt even bigger and more comfortable. 

I can't decide if my brain just needed to adjust from my imagination to reality, from 2-dimensional plans to 3-dimensional space, or if there was some kind of cognitive block in my brain that meant I couldn't accurately gauge the volume of space when it was outlined without being enclosed. In either case, it was strange and unsettling, and I'm glad it passed. This project is way too major to have to live with discontent or disappointment about it!

Of course, I am curious to see how it feels once the walls are closed all the way in and the roof is on, as that will make a change yet again, I'm sure. 
Day 4
I got more chances to spend time on the building site over the weekend, because some friends invited me to stay in their nearby house while they were away camping.

Interior space taking shape – I love that high window. The small opening lower down on the left is for my firewood pass-through. 
Light and shadow at my back doorway.
The view from my back door. 
I had a moment, sitting in the back doorway when I could feel what it's going to be like to live in my house, with a deck or even a little screened-in porch to the south, and maybe even a deck on the east side, as well. I foresee a lot of coziness and peace and quiet, safety and comfort, protected and blessed by these trees.

I have been yearning for a home of my own for a long time. I feel very lucky and humbled and I am deeply, deeply grateful to all of the people and circumstances that are making this possible.