Pages

Showing posts with label excavation. Show all posts
Showing posts with label excavation. Show all posts

Tuesday, December 12, 2017

Construction: Weeks 9, 10, 11 and 12

I have been struggling to write this blog post. It has been postponed from week to week.

I have been busy, doing a lot of manual labour out at the site and a lot of desk work the rest of the time. And these weeks have felt challenging; I have been frequently overwhelmed.

Rather than not writing a blog post about these weeks at all, I am resorting to a classic cheat borrowed from William Goldman's A Princess Bride:

What with one thing and another, four weeks passed:

I had some trouble finding someone willing to dig my well and install my septic system, but fortunately, my plumber was able to recommend someone excellent. We walked the land and he recommended the place for the well, very close to the massive felled maple log that was dropped when my power lines were installed last year. It was going to need to be cut up and moved. So, I boldly set about cutting it into shorter logs with my small chainsaw. At one point, I pinched my saw and had to free it with a hand saw. One of the joys of being a rookie... 

A rare view of the low side of the cabin.


In Week 9, the cabin was wired
Roxul insulation getting stockpiled

Week 10: Excavator, on the job!
The septic tank
The septic field
The septic system covered with fill, seeded with clover and covered with hay.
Guess what got dug up? Rocks! Now placed aesthetically along my driveway
Meanwhile, in the house, the interior walls were being insulated. 

And I drove to Ross Farm museum to pick up the barn door hardware they had made for me.

Here's the hatch for my firewood pass-through.

The excavator, resting after its labours.
I take a time-out to appreciate the beauty of a wee, still-red oak
Over the weekend between Weeks 10 and 11, the house sees its first light dusting of snow
Week 11: The well gets dug.

 They went down about 14 feet and there was so much water that the excavation crew could hardly level the first crock before the water was threatening to come in over their boots. Here is the well after the concrete apron has been poured. (The next day the water rose up over the apron!) I feel like I have won the rural home lottery! 




My awesome plumber comes and installs the well-line and pump
Bright blue well line for the water and rainbow electrical wire for the pump – pretty! 

Next, the trench was dug for the well-line. We hit a snag here, but I don't want to talk about it. Suffice it to say, we got through it. 

Guess what else got dug up? More rocks! Including some really, really big ones.

Meanwhile, I was working on augmenting the insulation around the slab, having fun with an exacto knife and a pickaxe.

And inside, the insulation and vapour barrier were complete and the drywall was delivered and stored ready for the following week.

Week 12 began with the site in a great big mess.

(Trenches can be beautiful, though).

With the trench for the well line dug and filled back in, next was the trench to bring power from my shed to the house. 
The electrical cable and the conduit containing my internet cable had to be seated in sand and inspected before the trench could be filled back in.

Where the electrical service enters the cabin.

In the cabin, the drywall was going up.

Outside, I was unearthing some pretty big rocks in the process of regrading the land around the house to lay insulation out two feet from the slab at an angle of 4 degrees (or more). Some of the rocks were too heavy for me to move. Fortunately, my stellar carpentry crew helped me roll the biggest ones out of the way.

Here's one corner of the insulation around the outside of the slab.

On the last day of the excavation work, my well and septic contractor brought me a load of Class A as a bonus – I will use it to backfill against my house, over the slab insulation. 
While putting together the photo essay portion of this post, I think I have found a few words to say. 

These four weeks felt intense. I was on-site a lot. On the one hand, it was lots of fun to be at the heart of the action. I really like all of the people working on the project, so it was great to hang out and indulge in a little banter.

At the same time, though, I was working hard: digging, digging and more digging. It was good for me, but at the same time exhausting and hard on my joints. (I've started going to see a chiropractor again after a 7-year break and it is rescuing me from immobilization).

While it was physically grueling, it didn't require any particular skills. It was a part of the job that I could do, and I needed to invest all the sweat equity that I could because somewhere in these four weeks, I ran out of money. Which is to say that I ran out of my money, money that I had or had access to on my own responsibility.

This project has been more expensive than I hoped. That is always said of building projects and that's because it's probably always true. There is so much to do, especially so much infrastructure to establish for a rural house.

Fortunately, I have friends and family to help me out and they have encouraged me to keep going. Many have provided moral support and encouragement, some have loaned tools and equipment, others have given their time to help, some have loaned and some have given me money to help make it possible for me to complete this project. I feel very, very lucky and very, very grateful.

And at the same time, I'm pretty stressed. I didn't want to take on this much debt. I foresee some austerity measures and as much desk work as I can get my hands on for the next 3-5 years.

I do feel, though, that it is worth it. I have such a longing for a home of my own. It is starting to feel very real; I am getting to the point where I can visualize living in my home: reading, doing jigsaw puzzles, having dinner parties and summer visitors. Having a place to be myself, to be content, to be free and safe and peaceful.

And what a place it is. The Crooked Wood continues to provide me with a blessed sense of belonging. Each time I arrive there and breathe that first breath of forest air, I feel something sacred fill me: mind, body, heart and soul.

The thought of being able to live in my own home, cozily, year round, is worth the debts and the stresses and the challenges of this process.

It's simply where I feel I'm meant to be.

Monday, October 2, 2017

Construction: Week 2

This process is getting smoother as it goes along. It took me almost a whole week before I managed a report on Week 1 and here is the Week 2 update after just a couple of days. 

On Monday, last week, my amazing friend and another amazing friend of ours came to spread several tons of Class C and Class A gravel to extend the pad around the foundation. We had to hustle because the crew was coming to build the form at 2pm. So, hustle we did and we got 'er done in time. 
The pad at the beginning of the form's construction.
The form had to be meticulously measured to make sure it was a rectangle and not a parallelogram. I was proud to see that our measurements were very close to the pros'. As the form was built, it had to be leveled, too. A couple of our corners were a few inches lower than the others, but it was nothing that a little crushed rock couldn't fix.
No fair! They had a rock "slinger" and filled the form with gravel in a fraction of the time that it took us to spread gravel for the pad!
Three-inch thick and 2-foot wide foam insulation was placed around the edges on the inside of the form. The centre was then filled with gravel up to the edges of the insulation.
On Tuesday, the plumber came to install the under-slab plumbing. It was an unbelievably hot day for late September in Nova Scotia. Actually, it was an unusually hot day for Nova Scotia – period. To reduce the risk of my plumber passing out from heat exhaustion, I pitched in to help dig channels in the gravel to place the pipes and then helped fill in around them. Even sharing the work, we had to take several breaks for water and popsicles.
It's a small job – one 3-piece bathroom and a kitchen sink, but it's still a lot of pipes...


Once the under-slab plumbing was done and inspected, the slab contractors had to come back to do the next steps.
Stakes and pieces of 2x4 bolster the sides of the form, so it won't fall apart when the concrete is poured.
Insulation is fitted over top of the gravel and pipes.
Rebar and wire mesh are added to reinforce the concrete.
Surprise! The plumber needed a wooden box to put around the shower drain to keep it free of concrete and allow him some wiggle room to place the drain correctly under the shower pan. I had no idea this would be necessary, but fortunately, my builder was able to build the box on short notice and the slab contractors cut the angle to fit the slope of the insulation.
To recap, the following steps were completed during Week 2:
  1. Excavation
  2. Construction of the form
  3. Under-slab plumbing
  4. Under-slab plumbing inspection
  5. Insulation and wire mesh
I felt much more steady during Week 2 than I did during Week 1. Working with friends the first week gave me the safety to meltdown and be supported in my doubts and fears. Now that things have moved into the hands of strangers, I'm rising to the to occasion and pulling myself together a bit more. It helps that I feel like I am developing a better handle on this process. Learning what to expect and what I can do to help facilitate things is helping me maintain a more positive and relaxed attitude.

It helps that the contractors working with me (and their crews) have been stellar, fitting this project into their schedules with virtually no delays. It feels like a complicated process to weave all of these inter-dependent tasks, but so far, it's been almost seamless, and that is helping to build my confidence. 

I'm optimistic about Week 3. If things continue in the same vein, the slab should be poured by the end of this week! (knock wood)

Friday, September 29, 2017

Construction: Week 1

Mumma, for why all these changes?
Well, after months of planning, designing, stressing, worrying and lining up contractors and estimates and quotes, the ball finally started rolling last week. 

I had found a contractor to pour the slab for my foundation, but I couldn't find anyone who was available to do the excavation. It feels like the entire south shore of Nova Scotia is madly building, trying to get things done before the snow flies and contractors are busy, busy, busy! I feel lucky to have found the great bunch of contractors who've agreed to work on this project, but I struck out trying to find a excavation contractor who was available, affordable and with whom I felt comfortable. And without the excavation work, nothing could move forward.

Luckily for me, my friend of the amazing chainsaw skills has myriad other skills and offered to do the excavation work I needed to have done. Not that he's not extremely busy, too, but he made the time so that work at my place wouldn't be held up – a tremendous and generous gift to me.

The first task was "scrubbing off" the organic matter, dead and alive.
It was a perfect opportunity to take logs that had been cut over the past year and a half to make way for the driveway and power lines and load them on the trailer to go off to be milled into useful lumber.
One of the limbs had to be removed from old Father Maple so that the big trucks would be able to back right up to the form. He remains a stately, if somewhat less crooked, presence. 
We had to have a couple of loads of shale delivered.
And my friend brought tons of gravel in his truck and trailer, too... 
...much of which we spread by hand using shovels, rakes and buckets.
I got to drive the excavator when the right-rear wheel of the truck went over the edge of the driveway and the truck had to be assisted back onto solid ground.
The awesome slab contractor loaned us his transit level so we could check how level the pad was as we spread the gravel. 
A DEEP trench had to be dug for the well line to go out from the house. You never think how deep 4 feet is, but it's deep enough when you're trying to dig through rocky South Shore Nova Scotian soil! 
I'm not going to lie to you, I melted down more than once last week. I felt so overwhelmed. I wished that I had never had the temerity to think that I could organize having a small cabin built for myself.

Days were spent leveling ground, moving logs and getting gravel in place. Despite being worn out by the work, I did not sleep well, waking up in the middle of the night with anxious thoughts like, "What am I doing?" and "Why did I decide to do this?"

There were some shaky, miserable hours. Fortunately, a number of people close to me provided moral support and tangible help, often exactly when it was needed most.

And there were some exiting moments, too. I invested in a chain saw and used it for the first time ever! And I drove the excavator. And I worked: healthy, outdoor, physical labour.

As the work progressed, I started to feel better. Excavation was hard – it felt like we were ripping the land to pieces. Fortunately, after ripping it apart, we started to put it back together again. And for me, as that happened "Why am I doing this?" and "What am I doing?" transformed into "I am doing this."

The definiteness of that is a lot more comfortable than sitting in the unknown of doubts and second guesses.

And since I am doing this, I want to embrace the process. After several wobbly weeks, I've come to understand that if I want this house to be built wholeheartedly, by people who are kind and easy through the process, that means that I have to find kindness and ease in my heart, too.

Otherwise, there is no point.



This construction project requires Salinger to be vigilant and alert. On Friday, when all the machines had gone away for a bit, he had to have some serious naps to recover from all of the excitement.