Pages

Monday, October 23, 2017

Construction: Weeks 4 and 5

BIG Weeks!

Weeks 4 and 5 were two major weeks. I was too overwhelmed and busy during and between them to write a blog post, so am putting both weeks together in one post now (at the beginning of Week 6). 

Somewhere in the middle of it all, Salinger and I reluctantly moved house, back into our winter digs in Lunenburg. While we are incredibly lucky to have these friendly and comfortable accommodations available to us for the third winter in a row, it was still a bad wrench to leave The Crooked Woods. But my little tiny house was getting chilly and starting to have problems with moisture and condensation and it was time to head for central heating.

Week 4

Week 4 was SLAB WEEK! This was one of the most nerve-wracking stages of the build so far. Pouring concrete is something you want to get right the first time. Second chances at a pour are virtually impossible. Also, if the cement truck can't access the site, there's a big financial penalty and then more work to do to make the site accessible. 

Fortunately, the cement truck was able to get back to the form on its first attempt, thanks to my amazing friend who widened out the driveway and cut a low limb off the big maple during Week 1.
Distributing the cement to the rear section of the form is heavy work, done by wheelbarrow. The work speeds up once the concrete can be poured directly from the truck's chute into the form.
All poured, partly trowelled
Power-trowelling!
The finished slab. I love the marbled look it has. 
The slab needed to be kept wet for three days to discourage cracks from forming. My rain barrel, a bunch of bed sheets and a big tarp helped with this task. Salinger putting his fluffy backside on the wet sheets was probably counter-productive, but very, very cute.
The ever-deepening chill was a big factor in deciding that it was time to move out to my friend's house in Lunenburg. Here is the radiant heater running full blast in the tiny house while I tried to get some desk work done in the early morning on one of my last days living on site...
The sub-contractors who worked on the slab were fantastic to have on site, continuing my lucky streak of skilled and friendly people working on this project.

Week 5

With the slab poured and set and inspected, the framing could begin. There was a risk of rain on Monday, so the work began on Tuesday, and holy cats, did it ever go quickly with four people on the crew and four days of gorgeous fall weather!!! 

Day 1 of framing
Detail, Day 2
End of day 2!
I was stuck in Lunenburg doing desk work on Day 1, but managed to get to the site to spend the morning on Day 2 and then stopped in for quick visits on Day 3 and again on Day 4. 

I was delighted on Day 2 to watch how the four-person crew functions as a well-oiled machine. Everyone had their tasks to meet the inter-locking requirements of the build. Boards needed to be selected and cut and placed and secured and I found it a graceful, intricate dance to watch. And I love the energy with which the crew works – music on the radio, banter back and forth, questions and answers – it all seems to flow with ease and enthusiasm. 

The best contribution I could make was to stay out of the way! So, I turned my hand to sorting out a bunch of paperwork to do with the build and making sure that all of the permits and plans would be readily accessible when I wasn't there. 

I had an unsettling feeling on Day 2. I walked around inside the framed space and was filled with a sense of panic – "It is TOO small!" I thought. "What have I done? What am I doing? I'm having something built that I'm going to HATE living in. Oh NO!!!!!"

Day 2, side view

But then, weirdly, when I came back at the end of Day 3 and two of the walls were sheathed with OSB, enclosing the building somewhat, it felt larger, rather than smaller. I felt perfectly comfortable, and thought "Oh, yes, this is exactly what I thought it would be like; this is plenty of room!"

And when I came back on Day 4, when all four walls were closed in to a height of 8 feet, the space felt even bigger and more comfortable. 

I can't decide if my brain just needed to adjust from my imagination to reality, from 2-dimensional plans to 3-dimensional space, or if there was some kind of cognitive block in my brain that meant I couldn't accurately gauge the volume of space when it was outlined without being enclosed. In either case, it was strange and unsettling, and I'm glad it passed. This project is way too major to have to live with discontent or disappointment about it!

Of course, I am curious to see how it feels once the walls are closed all the way in and the roof is on, as that will make a change yet again, I'm sure. 
Day 4
I got more chances to spend time on the building site over the weekend, because some friends invited me to stay in their nearby house while they were away camping.

Interior space taking shape – I love that high window. The small opening lower down on the left is for my firewood pass-through. 
Light and shadow at my back doorway.
The view from my back door. 
I had a moment, sitting in the back doorway when I could feel what it's going to be like to live in my house, with a deck or even a little screened-in porch to the south, and maybe even a deck on the east side, as well. I foresee a lot of coziness and peace and quiet, safety and comfort, protected and blessed by these trees.

I have been yearning for a home of my own for a long time. I feel very lucky and humbled and I am deeply, deeply grateful to all of the people and circumstances that are making this possible. 

Tuesday, October 10, 2017

Construction: Week 3

Well, last week was rather up and down.

There was a lot of hanging around waiting for things to happen; it felt frustrating and tedious by times.

The plumber was unable to come on Monday, but I couldn't go anywhere because I was waiting for the inspector to come and ok the under-slab insulation and vapour barrier. She came in the mid-afternoon and signed off, so that was good.

My plumber came with an assistant on Tuesday morning to install the in-floor heating pipes.
So neat and orderly.
The pipes are all zip-tied to the wire mesh.
Once all of the pipes were in, the plumber pressurized them with an air compressor to make sure there were no leaks.

My plumber came back on Wednesday to bring me my shower pan and invoices for the work of roughing in the plumbing.

My builder came on Wednesday, too, to have a look at the heating pipes and take photos and measurements, so they can be sure when they anchor the walls that none of the in-floor heating pipes will get ruptured.

The slab contractors weren't able to come on Wednesday OR Thursday – there was just no space in their schedule.

Wednesday was not a fun day. I was in a terrible mood and didn't feel like going anywhere or doing anything.

I felt a bit more upbeat on Thursday, but I still couldn't go anywhere because I was waiting for the first delivery of materials. Since the concrete truck still needs to be able to back up to the form, the materials have to be placed properly on the site, so they won't all have to be moved out of the way when the concrete truck comes. There is a hefty penalty if the concrete truck comes and can't access the site.

The boom truck is pretty cool.
Tucked out of the way for the time being...

Bad news

I received a couple of pieces of bad news on Thursday. For one thing, although the slab crew would come on Friday morning to make their final preparations, it would be Tuesday before the building inspector would be able to come sign off – and therefore Wednesday (at the earliest) before the concrete could be poured. So more waiting was on the cards.

Also, the results of my Efficiency Nova Scotia New Home Construction Program Review came in and showed that there was nothing feasible I could do to be eligible for rebates for my project. My Energuide rating works out at an 82, and there is not much I can do at this point to push it over the threshold for rebates, which is 85. This is partly my fault, because I waited too long to do the assessment – essentially, after making inquiries about it earlier this summer, I then forgot all about needing to do it until a couple of weeks ago... If I had done the assessment before my design had been decided, I might have been able to make changes that would have brought me up to an 85. But, not necessarily. My house is so small that changes to the mechanical systems don't have much impact. Also, the base load in the model is for two adults and a child, rather than one adult and a cat. So, I will doubtless be more efficient in my home than the model shows, but bureaucracy doesn't work like that and there will be no money back from the government for me.

On the plus side, the assessment was done by a friend of mine who works in the energy efficiency industry and we got to have some nice chats as we went back and forth discussing questions and options.

By the end of the day on Thursday, I was in an even grimmer mood than I had been on Wednesday. Fortunately for me, a friend came, helped me get my newly-delivered doors into my shed for safekeeping, took me to play tennis for the first time in years (which was super fun) and then to a party with many of my favourite people.

Next steps

I was in a much better mood on Friday and happy to see the slab contractors come back and finish installing the rebar for the project. I sent photos to the engineer who had designed the slab and he was impressed by the execution.

Continuous lap rebar
The finished underslab
Steps 6, 7 and 8 of the slab got completed this week. Just two more steps to go!
  1. Excavation (Week 1)
  2. Construction of the form
  3. Under-slab plumbing
  4. Under-slab plumbing inspection
  5. Insulation and wire mesh (Week 2)
  6. Inspection
  7. In-floor heating pipes
  8. Rebar
  9. Inspection
  10. Concrete pour
I paid for the excavation and the first phase of the plumbing this week. Money is flowing out quickly now, as I knew it would. This project has not felt particularly blessed financially. The bank declined to extend my line of credit. There will be no rebates from Efficiency NS. This makes me all the more thankful to my friend who gave me a sweet deal on the excavation work, and who is also willing to dig a well for me when the time comes. And I am deeply grateful to a couple of dear people who have offered me short-term loans if I get in over my head. 

Ever changing moods

I notice my moods have been cycling more rapidly than usual, which feels challenging. I struggled through the early part of last week, was very chipper Thursday eve through Saturday eve and then quite depressed again on Sunday and Monday over the holiday weekend. I think this is a combination of hormones and the stresses of this undertaking. I have wished, more than once, that I had had the foresight to know that I should build a cabin immediately after landing back in Nova Scotia, when it would have been less expensive and when I was not yet into the emotional rollercoaster of peri-menopause. I feel that many times in my life, I've gotten ready to do things (my personal chef business, my music career) years later than would have been optimal. But, I'm here now. And I'll get through this. While it might have been easier seven years ago (or 10 or 20), it was also not possible for me then – if it had been, I would have done it.

Here I am, in the present moment, taking things day by day – or hour by hour, when that's necessary. Sometimes, I'm in a crappy mood and feel overwhelmed and anxious. And sometimes I'm in a great mood and feel like I can manage everything just fine. And that, my friends, is my life these days.

Lumber is Salinger's favourite camouflage.

Monday, October 2, 2017

Construction: Week 2

This process is getting smoother as it goes along. It took me almost a whole week before I managed a report on Week 1 and here is the Week 2 update after just a couple of days. 

On Monday, last week, my amazing friend and another amazing friend of ours came to spread several tons of Class C and Class A gravel to extend the pad around the foundation. We had to hustle because the crew was coming to build the form at 2pm. So, hustle we did and we got 'er done in time. 
The pad at the beginning of the form's construction.
The form had to be meticulously measured to make sure it was a rectangle and not a parallelogram. I was proud to see that our measurements were very close to the pros'. As the form was built, it had to be leveled, too. A couple of our corners were a few inches lower than the others, but it was nothing that a little crushed rock couldn't fix.
No fair! They had a rock "slinger" and filled the form with gravel in a fraction of the time that it took us to spread gravel for the pad!
Three-inch thick and 2-foot wide foam insulation was placed around the edges on the inside of the form. The centre was then filled with gravel up to the edges of the insulation.
On Tuesday, the plumber came to install the under-slab plumbing. It was an unbelievably hot day for late September in Nova Scotia. Actually, it was an unusually hot day for Nova Scotia – period. To reduce the risk of my plumber passing out from heat exhaustion, I pitched in to help dig channels in the gravel to place the pipes and then helped fill in around them. Even sharing the work, we had to take several breaks for water and popsicles.
It's a small job – one 3-piece bathroom and a kitchen sink, but it's still a lot of pipes...


Once the under-slab plumbing was done and inspected, the slab contractors had to come back to do the next steps.
Stakes and pieces of 2x4 bolster the sides of the form, so it won't fall apart when the concrete is poured.
Insulation is fitted over top of the gravel and pipes.
Rebar and wire mesh are added to reinforce the concrete.
Surprise! The plumber needed a wooden box to put around the shower drain to keep it free of concrete and allow him some wiggle room to place the drain correctly under the shower pan. I had no idea this would be necessary, but fortunately, my builder was able to build the box on short notice and the slab contractors cut the angle to fit the slope of the insulation.
To recap, the following steps were completed during Week 2:
  1. Excavation
  2. Construction of the form
  3. Under-slab plumbing
  4. Under-slab plumbing inspection
  5. Insulation and wire mesh
I felt much more steady during Week 2 than I did during Week 1. Working with friends the first week gave me the safety to meltdown and be supported in my doubts and fears. Now that things have moved into the hands of strangers, I'm rising to the to occasion and pulling myself together a bit more. It helps that I feel like I am developing a better handle on this process. Learning what to expect and what I can do to help facilitate things is helping me maintain a more positive and relaxed attitude.

It helps that the contractors working with me (and their crews) have been stellar, fitting this project into their schedules with virtually no delays. It feels like a complicated process to weave all of these inter-dependent tasks, but so far, it's been almost seamless, and that is helping to build my confidence. 

I'm optimistic about Week 3. If things continue in the same vein, the slab should be poured by the end of this week! (knock wood)