Pages

Tuesday, December 12, 2017

Construction: Weeks 9, 10, 11 and 12

I have been struggling to write this blog post. It has been postponed from week to week.

I have been busy, doing a lot of manual labour out at the site and a lot of desk work the rest of the time. And these weeks have felt challenging; I have been frequently overwhelmed.

Rather than not writing a blog post about these weeks at all, I am resorting to a classic cheat borrowed from William Goldman's A Princess Bride:

What with one thing and another, four weeks passed:

I had some trouble finding someone willing to dig my well and install my septic system, but fortunately, my plumber was able to recommend someone excellent. We walked the land and he recommended the place for the well, very close to the massive felled maple log that was dropped when my power lines were installed last year. It was going to need to be cut up and moved. So, I boldly set about cutting it into shorter logs with my small chainsaw. At one point, I pinched my saw and had to free it with a hand saw. One of the joys of being a rookie... 

A rare view of the low side of the cabin.


In Week 9, the cabin was wired
Roxul insulation getting stockpiled

Week 10: Excavator, on the job!
The septic tank
The septic field
The septic system covered with fill, seeded with clover and covered with hay.
Guess what got dug up? Rocks! Now placed aesthetically along my driveway
Meanwhile, in the house, the interior walls were being insulated. 

And I drove to Ross Farm museum to pick up the barn door hardware they had made for me.

Here's the hatch for my firewood pass-through.

The excavator, resting after its labours.
I take a time-out to appreciate the beauty of a wee, still-red oak
Over the weekend between Weeks 10 and 11, the house sees its first light dusting of snow
Week 11: The well gets dug.

 They went down about 14 feet and there was so much water that the excavation crew could hardly level the first crock before the water was threatening to come in over their boots. Here is the well after the concrete apron has been poured. (The next day the water rose up over the apron!) I feel like I have won the rural home lottery! 




My awesome plumber comes and installs the well-line and pump
Bright blue well line for the water and rainbow electrical wire for the pump – pretty! 

Next, the trench was dug for the well-line. We hit a snag here, but I don't want to talk about it. Suffice it to say, we got through it. 

Guess what else got dug up? More rocks! Including some really, really big ones.

Meanwhile, I was working on augmenting the insulation around the slab, having fun with an exacto knife and a pickaxe.

And inside, the insulation and vapour barrier were complete and the drywall was delivered and stored ready for the following week.

Week 12 began with the site in a great big mess.

(Trenches can be beautiful, though).

With the trench for the well line dug and filled back in, next was the trench to bring power from my shed to the house. 
The electrical cable and the conduit containing my internet cable had to be seated in sand and inspected before the trench could be filled back in.

Where the electrical service enters the cabin.

In the cabin, the drywall was going up.

Outside, I was unearthing some pretty big rocks in the process of regrading the land around the house to lay insulation out two feet from the slab at an angle of 4 degrees (or more). Some of the rocks were too heavy for me to move. Fortunately, my stellar carpentry crew helped me roll the biggest ones out of the way.

Here's one corner of the insulation around the outside of the slab.

On the last day of the excavation work, my well and septic contractor brought me a load of Class A as a bonus – I will use it to backfill against my house, over the slab insulation. 
While putting together the photo essay portion of this post, I think I have found a few words to say. 

These four weeks felt intense. I was on-site a lot. On the one hand, it was lots of fun to be at the heart of the action. I really like all of the people working on the project, so it was great to hang out and indulge in a little banter.

At the same time, though, I was working hard: digging, digging and more digging. It was good for me, but at the same time exhausting and hard on my joints. (I've started going to see a chiropractor again after a 7-year break and it is rescuing me from immobilization).

While it was physically grueling, it didn't require any particular skills. It was a part of the job that I could do, and I needed to invest all the sweat equity that I could because somewhere in these four weeks, I ran out of money. Which is to say that I ran out of my money, money that I had or had access to on my own responsibility.

This project has been more expensive than I hoped. That is always said of building projects and that's because it's probably always true. There is so much to do, especially so much infrastructure to establish for a rural house.

Fortunately, I have friends and family to help me out and they have encouraged me to keep going. Many have provided moral support and encouragement, some have loaned tools and equipment, others have given their time to help, some have loaned and some have given me money to help make it possible for me to complete this project. I feel very, very lucky and very, very grateful.

And at the same time, I'm pretty stressed. I didn't want to take on this much debt. I foresee some austerity measures and as much desk work as I can get my hands on for the next 3-5 years.

I do feel, though, that it is worth it. I have such a longing for a home of my own. It is starting to feel very real; I am getting to the point where I can visualize living in my home: reading, doing jigsaw puzzles, having dinner parties and summer visitors. Having a place to be myself, to be content, to be free and safe and peaceful.

And what a place it is. The Crooked Wood continues to provide me with a blessed sense of belonging. Each time I arrive there and breathe that first breath of forest air, I feel something sacred fill me: mind, body, heart and soul.

The thought of being able to live in my own home, cozily, year round, is worth the debts and the stresses and the challenges of this process.

It's simply where I feel I'm meant to be.

Saturday, December 9, 2017

Galway #banjoy

Someone who knows me well shared this link on my Facebook page and the #banjoy that resulted was worthy of a post here:

https://www.independent.ie/entertainment/banter/trending/watch-sensational-byrne-brothers-bring-galway-street-to-a-standstill-36387732.html

Enjoy!

Monday, November 13, 2017

Construction: Weeks 6, 7 and 8

These were three more big and periodically overwhelming weeks. 

Week 6

Progress continued to be rapid in Week 6, with the cabin quickly getting sheathed and wrapped, in time for a couple of stormy days.  

All closed in. Photo courtesy of Anckaert Built

That's a wrap! Photo courtesy of Anckaert Built.
Week 6 ended on a bumpy note. The locks I'd purchased for the doors didn't fit in the holes that had been drilled in the doors. I had failed to specify the size of the holes when I ordered the doors, so they had reverted to the default size, which I didn't realize would be different from the holes in the door of my shed. So, when I bought the same kind of locks, they didn't fit. 

I admit that I had a meltdown that day, in the parking lot of the Superstore in Bridgewater. Not very fun, or pretty to look at. Often, it is difficult for me to make mistakes or feel like I am out of my depth. And there has been more than enough of that in this project. The learning curve is steep. The problem with the locks was not high stakes, but it felt that way to me on that Friday afternoon.

Fortunately, I keep learning how to ride my own emotions more gracefully. And after talking with people in every hardware store in town, none of whom seemed to have the least clue about how locks are installed or what the measurements on the packaging referred to, I felt quite a bit better. I mean, if it's part of their job and they don't know, it seems more than fair that I don't know either. 

On Saturday, in my absence, the slab contractors came back and added styrofoam to the outside edges of the slab. I would have liked the styrofoam to extend a little further down – I plan to correct that when I add the insulation "skirt" to the building. 



Week 7

The beginning of Week 7 felt about the same as the end of week 6. I came over on Monday morning with new sets of locks and doorknobs, but I wasn't able to install them, because the doors needed to be prepped first and that lies a bit too far beyond my skill set and comfort zone.

The crew wasn't on site that day because of the rain, rain that came with high winds that later on blew a tree down on the power line that runs from the road to my shed:



So, there was no power on site Tuesday morning, which meant that the crew were only able to work a half-day until the batteries wore down on their tools. 

On the plus side, they were able to use some of that time get the locks installed, so my house is now lockable. 

Two more keys to add to my strangely large (and strangely beloved) ring of keys.

I came over in the afternoon on Tuesday and hung around waiting for the power company crew to show up and fix the lines. Fortunately, it was warm enough that I could sit outside and do deskwork most of the afternoon.


Expected restoration time for my power was 3pm, then updated to 6pm. Shortly before 6 pm, the forestry crew showed up and deftly cut the tree off the lines, bless them. My restoration time was updated to 9pm and I went home.

Before I went to bed, my restoration time had been updated to 11pm. I was afraid that it was going to keep getting pushed back into the next day, but fortunately, in the morning, power had been restored and work could resume at full tilt. 

For the construction crew, Week 7 was all about strapping and adding trim. I didn't come back to the site until Friday afternoon. 

The Heart of this project

As I got out of my car, I was struck by the delicious smell of The Crooked Wood. I had parked in the turnout to keep the driveway clear for the other folks on site. So, I strolled down the driveway and was greeted by the sound of music and banter and the sight of the crew working cheerfully and efficiently. I have a huge sense of gratitude for all of the good energy that I feel is being infused into my home, with each board and nail, each piece of siding and sheet of metal. 

My tiny house was converted by a very good-hearted person; I feel that energy all the time when I'm in Wholehearted House. I knew it was important to me to have good-hearted people work on my permanent home, too. 
• • • 

I spent the afternoon of that last Friday of Week 7 sanding down the door that I bought on Kijiji which is going to be hung, barn-door style, at the entrance to the bathroom. I love this door – with a single pane of textured glass, it reminds me of a door to a private investigator's office in a typical noir film from the 40s. 

Sanding is relaxing.
I love how distressed this big ol' monster is. 
In addition to the work that can be seen happening in these photos, I was also trying to figure out solutions and get estimates for work on digging the well and septic system. There are a lot of challenges there, many of which I'm still working through. There were moments when I felt extremely frustrated with red tape and with people not getting back to me.

The cabin at the end of Week 7
A little autumn beauty spot in #TheCrookedWood. I love how oak trees are among the last to lose their leaves. 
Naked maple
Week 8 went somewhat more smoothly. There was more progress and the crew were able to start putting the siding on the exterior. There were also more rain days, and for me, more frustration trying to nail down the situation with the well and septic. But there were no more downed power lines! And I call that an improvement!

I wasn't on-site much myself during Week 8. I had desk work to do and it has gotten too cold for me to sit still and work on the site. And, there wasn't much I could contribute by being there, so I mostly kept out of the way.

The plumber came and did the behind-the-walls plumbing.

I imagine most people don't find this kind of infrastructure beautiful, but I do. It's so neat and orderly and enables me to envision what the finished bathroom is going to look like.





And, here's the exterior of the house at the end of Week 8. 

My outdoor tap in the foreground <3
Looking good! I don't want to tempt the fates by saying this, but I think I might be halfway through...